Water-Sewer-Reuse Project: Street by Street Summary 11/17-11/23 (Updated)
 
Published Thursday, November 19, 2009 1:00 pm
by H. Groschel-Becker>

The Village Water/Sewer/Reuse (WSR) Project team is pleased to provide a weekly street-by-street activity summary as part of our public outreach program. This information will let residents know what to expect in the next week.  If you prefer to get your information via email, sign up at sewerinfo@keybiscayne.fl.gov. Please include your address so we can tailor the message for your residential area.

NOTE: Please direct all WSR communications, including questions and complaints, to Pietro Giacalone, the Project Field Inspector.  His mobile phone number is (305) 216-5750 and his email address is pietrog@c3ts.com. Project officials can serve residents more efficiently if all information requests are made to a central person. Thank you.

NOTE:
West Mashta Residents - We need the locations of your septic tanks so that the new sewer system lateral to your property line is installed at the correct location. This information is missing for most of the homes along the street. Those residents do not provide their septic tank locations are hereby notified that the sewer lateral will be installed to the property line by the contractor according to the project plan.

A tell-tale sign of the septic tank is the clean out pipe protruding above the grass. Residents are advised to contact a plumber or their clean-out service provider for assistance if necessary.

Please call Pietro Giacalone, the project Field Inspector for Zone 2/3, with your septic tank location information at (305) 216-5750 or email him at pietrog@c3ts.com
NOTE: Miami-Dade County gave the go-ahead for residents in Zone 4 (Holiday Colony) to connect to the new sewer system on September 10. Sewer Connection Process Guidelines for Residents (PDF document) are posted on the Village website. (UPDATE: Revised guidelines were posted on November 11, 2009.)

Residents are invited to attend weekly Zone 2/3 progress meetings at 10:30 a.m. on Tuesdays to voice concerns or ask questions. The meetings are held in the Building, Zoning and Planning Conference Room of Suite 250 at Village Hall.

Zone 1/Zone 4 weekly meetings were discontinued as of November 25, 2008. Construction work is complete, water service has been switched to new pipes in both zones, and Zone 4 sewer certification is complete. Residents will soon be able to start the hook-up procedure. Zone 1 as-built sewer drawings remain under review at Miami-Dade Water and Sewer Department; certification will be completed following their approval. The upgraded Pump Station 131 is the subject of monitoring for H2S odor (see June 20, 2009 letter from the Village Manager (PDF file) to residents in the area of PS 131 for details).
The Reuse Water weekly meetings were discontinued as of November 2008. Construction and restoration are complete, and only minor punch list items pertaining to submittal of as-built drawings and certification remain to be fulfilled.

PROJECT AREA MAP:

Need to know where your street is relative to the WSR work zones? See the limits of Zones 1, 2/3 and 4 on this map of the project area (PDF file).

IMPORTANT CONTACT INFORMATION:

Residents in Zone 2/3 construction zones with questions or complaints should call Pietro Giacalone, the Field Inspector for Project Manager C3TS, at (305) 216-5750. Please be advised that contractors may work on Saturdays within the limits of the Village noise ordinance (Contractor for Zone 2/3: Trans Florida). 

For water service emergencies (6:00 p.m. to 6:00 a.m.) please call the Miami-Dade County Water and Sewer Department (WASD) at (305) 274-9272.

PUBLIC SAFETY ANNOUNCEMENT:

Residents are strongly advised to STAY OUT OF CONSTRUCTION ZONES for their own safety. Please do not cross into areas defined by caution tape, barricades, cones, etc. Parents - please do not allow your children to play in or around active construction areas.

Project officials realize that space is tight with active trenching underway, as heavy equipment, steel plates, pipes and other equipment take up most of the right-of-way. The contractors have implemented a plan for pedestrian circulation in affected areas via demarcated pathways along property lines.

REQUEST FOR SEPTIC TANK LOCATIONS:

ALL ZONE 2/3 Homeowners: We need the locations of your septic tanks so that the new sewer system lateral to your property line is installed at the correct location. A tell-tale sign of the septic tank is the clean out pipe protruding above the grass. Residents are advised to contact a plumber or their clean-out service provider for assistance if necessary. You may call Pietro Giacalone, the project Field Inspector for Zone 2/3, with your septic tank location information at (305) 216-5750 or email him at pietrog@c3ts.com.
Those residents do not provide their septic tank locations are hereby notified that the sewer lateral will be installed to the property line by the contractor per design specifications as work proceeds street by street.

ROAD RESTORATION OVERVIEW: Once sewers are installed, crews will begin restoring the roadway as follows:

  • Work begins with excavation of the road to the new base level, placement of lime rock, and grading of the rock. Rims of manhole covers will be aligned to align with the new road surface, and curbs (if any) will be poured. Miami-Dade County Water and Sewer Department (WASD) will complete their testing for certification of the new water and sewer pipes during this time. The final step is the placement of the first layer of asphalt to make a level, clean driving surface.
  • The next phase includes restoration of items in the public right-of-way, including swale landscaping (to Village specs), driveways, walkways and mailboxes/posts.
  • The final layer of asphalt (3/4" thick) will be placed once all restoration work is complete.
  • Private property concerns will be addressed at the end of work in respective zones. Property owners are advised to contact the Department of Public Works at (305) 365-8945 to report any damage related to the WSR project.

LIST OF QUALIFIED PLUMBERS REGISTERED WITH THE VILLAGE:

An updated (as of February 2009) list of qualified plumbers (PDF file) registered with the Village Building, Zoning and Planning Department is available for homeowners who will hook up to the new sewer system and will abandon their septic tanks. These plumbers have worked in the Village in the twelve months prior to February 2009.

NOTE: Distribution of this list is in no way an endorsement by the Village of one company over another. The information is provided as a service to residents.

REUSE WATER (PURPLE PIPE) PROJECT:

The Miami-Dade Water and Sewer Department (WASD) began installing reuse water pipes from Calusa Park along Fernwood Road to West Mashta Drive on June 18, 2008. WASD Officials held a public meeting at the Village Council Chamber at 7:00 p.m. on Wednesday, June 18, 2008. The target audience was residents and business people in the installation area who may hook up to the reuse water pipe in the future. More information is available in this letter (PDF) sent by WASD to these property owners.

STREET-BY-STREET UPDATES: 

From November 17-24, 2009
ZONE 1   STREET ACTIVITY
 

NOTE: Meetings with the contractor regarding sewer
certification continue. The revised set of sewer as-built
drawings were approved by WASD. Approval of final
conveyance document package pending; conveyance is
expected by the end of 2009. Residents will be able
to connect to sewer thereafter.

NOTE: 
Zone 1/Zone 4 and Reuse water weekly meetings
were discontinued as of November 25, 2008. Zone 1
construction is complete and water service has been
switched to the new pipes. The conveyance
procedure will begin once as-builts are approved and
the final inspection is complete. Residents cannot
hook up to sewer until this process is complete. The
Pump Station 131 hydrogen sulfide odor problem has
been addressed with the installation of an ozone pump
by WASD on June 26. See a June 20, 2009 letter to
residents in the area of PS 131 from the Village
Manager (PDF file)
for details about the issue.

  Area 1
West Matheson
Drive

WASD final review underway.

    Bay Lane WASD final review underway.
    Harbor Point
Drive

WASD final review underway.

  Area 2 Harbor Drive

WASD final review underway.

    Sunset Circle
WASD final review underway.
    Harbor Circle
WASD final review underway.
  Area 3
West McIntyre
Street
WASD final review underway.
    Satinwood Drive
(South segment)

WASD final review underway.

    West Enid Drive WASD final review underway.
    Curtiswood Drive

WASD final review underway.

  Area 4
Allendale Road

WASD final review underway.

    Sabal Palm Drive WASD final review underway.
    Satinwood Drive
(North segment)
WASD final review underway.
    Beechwood Drive

WASD final review underway.

       
ZONE 4

STREET ACTIVITY
  NOTE:  County approval for resdeints to hook up to
the sewer system was given on September 10, 2009.
A sewer connection guide (PDF document) compiled by the Village
is available online. A revised version
of this document was posted on November 19, 2009.

Zone 1/Zone 4 and Reuse water weekly meetings
were discontinued as of November 25, 2008. Zone 4
construction is complete and water service has been switched
to the new pipes. Conveyance of the new sewer system from
the Village to WASD occurred on August 24. 
    Caribbean Road

Sewer hook-up allowed.

    Gulf Road

Sewer hook-up allowed.

    Pacific Road

Sewer hook-up allowed.

   

Atlantic Road

Sewer hook-up allowed.

    East Heather
Drive

Sewer hook-up allowed.

    Sonesta Drive
Sewer hook-up allowed.
     
ZONE 2/3

STREET ACTIVITY
 

NOTE: Paving with the 2nd (final) layer of asphalt
will occur as soon as remedial concrete work is
completed and West Mashta between Fernwood
and Ridgewood is ready for the first layer of paving
in about 2-3 weeks. Roads slated to get the 2nd
paving pass include Harbor Drive north of West
Wood, Harbor Lane, West Wood and the 600
blocks of Curtiswood, Allendale, Warren, Hampton,
Woodcrest and Ridgewood.

NOTE: West Mashta Residents - Sewer work
is underway and we need the locations of
your septic tanks so that the new sewer
system lateral to your property line is installed
at the correct location. This information has not
been submitted for most of the homes along
the street. Those residents do not provide
their septic tank locations are hereby notified
that the sewer lateral will be installed according
to the project plan.

A tell-tale sign of the septic tank is the clean out
pipe protruding above the grass. Residents are
advised to contact a plumber or their clean-out
service provider for assistance if necessary.

Please call Pietro Giacalone, the project Field
Inspector for Zone 2/3, with your septic tank
location information at (305) 216-5750 or
email him at pietrog@c3ts.com.

NOTE:
According to current progress, physical
construction along West Mashta and the last
piece of Allendale will be complete by the end
of 2009. The earliest Zone 2/3 residents could
hook up to the new sewer is in March 2010.
This date is pending successful completion,
certification and conveyance to WASD of the
project. WASD has received paperwork from
project officials to certify new sewer and
water systems in 3 phases (geographic areas)
to speed up the process.  Phase 1 (between
West Heather and West Enid from Warren to
Fernwood, between West Wood and West Enid
from Allendale to Woodcrest, and the new
pump station, Key Biscayne K-8 Center
and the Community Church) water certification
is complete and service switched to new pipes;
as-builts for water, sewer and the pump
station have been submitted to WASD for review.
In Phase 2 (from West Wood to West Mashta
between Ridgewood and Harbor Drive, from
Harbor Drive to just south of Harbor Circle,
Harbor Lane, and Curtiswood and Allendale
north of West Wood), the water certification
process continues. Phase 3 includes the area from
West Wood to West  Mashta between Ridgewood
and Fernwood, Glenridge and Fernwood south
of West Enid, and sewer extensions east of
Fernwood along West Enid, West Wood and West
Mashta. Water pipe certification cannot be
completed until West Mashta sewer is done and
its new water main is connected to cross-street
pipes.

NOTE:
WASD is transferring water services to
meters located in driveways and sidewalks along
West Mashta and other streets. Expect local
detours. The old meter will be removed once
once the new meter is activated. Trans Florida
will then revisit the areas to restore them to pre-
project conditions.

NOTE: Please be patient with driveway restoration.
Tasks are performed by different subcontractors
specializing in brick pavers, poured or stamped
concrete, asphalt, etc. Not all repairs along a street
will be completed at the same time. For example,
all paver driveways/walkways will be repaired by a
paver specialist. Work on other types of surfaces will
be done on a different schedule by different
subcontractors.

NOTE: Residents in active work areas may
experience low water pressure or sporadic outages
during construction hours. Once service returns
after a water interruption, let the water run until
it is clear and air bubbles escape. You may prefer
to use an outdoor spigot or faucet for this process.
Sediment may clog the inside faucet filter so
periodic cleaning is advised.

  Yellow
(School)
Area
West Enid Drive
(south of school)

Paving with 2nd
layer, striping and
signage installation
is complete. Water
service was switched
from old to new
pipes. Water
and sewer main
installation is
complete.

    Ridgewood Road
(600 block)

Paving with 2nd
layer, striping and
signage installation
is complete. Water
service was switched
from old to new
pipes. Water and
sewer main
installation is
complete.

    West McIntyre
Street (100 block)

Paving with 2nd
layer, striping and
signage installation
is complete. Water
services were
switched from old
to new pipes. Water
and sewer main
installation is
complete.

    Glenridge Road
(mid-500-600
blocks)
Paving with 2nd
layer, striping and
signage installation
is complete. Water
services were
switched from old
to new pipes. Water
and sewer main
installation is
complete.
    West Enid Drive
(east of school)
Paving with 2nd
layer, striping and
signage installation
is complete. Water
services were
switched from old
to new pipes. Water
and sewer main
installation is
complete.
    Fernwood Road
(570-598 block)

Paving with
1st layer of asphalt
is complete. Water
services were
switched from old
to new pipes. Water
and sewer main
installation is
complete.

    West Enid Drive
(to new pump
station west of
school)

Paving with 2nd
layer, striping and
signage installation
is complete. The
final Pump Station
certification process
is underway.
Water services were
switched from old
to new pipes.
Water and sewer
main installation is
complete.

    West Wood Drive
(Ridgewood Road
to Hampton Lane)

Phase 2 water
certification is
complete. Paving
with 1st layer of
asphalt plus sewer
and water main
installation is
complete. 

       
  Green
(West
Central)
Area
West Enid Drive
(200 block;
west of pump
station)

Placement of 2nd
final layer of
asphalt is complete.
Water services were
switched from old
to new pipes.
Water and sewer main
installation complete.

    Hampton Lane
(600 block)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Water
services were
switched from old
to new pipes. Water
and sewer main
installation plus
paving with 1st
layer of asphalt is
complete. 

   

Warren Lane
(600 block)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Water
services were
switched from old
to new pipes. Water
and sewer main
installation plus
paving with 1st
layer of asphalt
is complete. 

    Allendale Road
(600 block)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Water
services were
switched from old
to new pipes. Water
and sewer main
installation plus
paving with 1st
layer of asphalt
is complete. 

    Curtiswood Road
(650-698 area)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews are repairing
driveways, curbs
and sidewalks.
New water pipe
certification is
done for this area.
Paving with
1st layer of asphalt
and sewer and water
main installation are
complete.

    West Wood Drive
(Hampton Lane
to Myrtlewood
Lane)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New
water pipe
certification is
done for this area.
Paving with
1st layer of asphalt
is complete.
Sewer and water
main installation
is complete.

    Curtswood Road
(700 block)

Paving with 1st
layer of asphalt
from from 755
area to Allendale
is complete. New
water pipe
certification data
are under review.
Paving with
1st layer of asphalt
and sewer and water
main installation is
complete.

    Allendale Road
(700 block)

Sewer installation
from West Mashta
to 780 area should
be completed by Nov.
20. Paving with 1st
layer of asphalt to
780 area is complete.
New water pipe
certification data
under review.
Sewer main
installation from
from West Wood to
780 Allendale and
is complete.
Water main
installation is
complete.

    Myrtlewood Lane

New water pipe
certification data
are under review.
Paving with 1st
layer of asphalt
complete.
Sewer and water
main installation
is complete.

    West Wood Drive
(Myrtlewood Lane
to Harbor Drive)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New
water pipe
certification data
are under review.
Paving with
1st layer of asphalt
is complete.
Sewer and water
main installation
is complete.

   

Harbor Drive
(West Wood Drive
to West Mashta
Drive)

New water pipe
certification data
are under review.
Road paved with
1st layer of asphalt.
Sewer and
water main
installation is
complete. 

    Harbor Drive
(West Wood Drive
to north of Harbor
Lane)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New
water pipe
certification is
done for this area.
Road paved with 1st
layer of asphalt.
Sewer and water
main installation is
complete.

    Harbor Lane

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New
water pipe
certification is
done for this
area. Road paved
with 1st layer of
asphalt. Sewer
and water main
installation is
complete.

       
  Orange
(North)
Area
West Heather
Drive (Fernwood
to Warren)
West Heather was
repaved as
planned after
completion of
sewer work along
side streets. 
 
Hampton Lane
(400-500 block)

Paving with 2nd
layer of asphalt
and sewer and
water main
installation
are complete.
Water services were
switched from old
to new pipes.

    Ridgewood Road
(400-500 block)

Paving with 2nd
layer of asphalt
is complete.
Sewer main
installation is
complete. Water 
pipes were
installed previously
(during storm
drainage project).

    Woodcrest Road
(400-500 block)

Paving with 2nd
layer of asphalt is
complete. Water
services were
switched from old
to new pipes.
Water and sewer
main installation is
complete. 

    Glenridge Road
(400-500 block)
Paving with 2nd
layer of asphalt
is complete.
Sewer main
installation is
complete. Water
pipes were installed
previously (during
storm drainage
project).
    Warren Lane
(400-500 block)

Paving with 2nd
layer of asphalt is
complete. Sewer
main installation is
complete. Water
pipes were installed
previously (during
storm drainage
project).

    Fernwood Road
(400-500 block)

Sewer manhole/
valves were raised
prior to paving along
Fernwood from the
422 area to Community
Church. Paving with
1st lift of asphalt is
complete in area
of first phase
of sewer main
installation.
Water services were
switched to new
pipes. Sewer
and water main
installation is
complete. 

    West McIntyre
Street (200 block)

Paving with 1st
layer of asphalt is
complete. Water
services were
switched to new
pipes. Sewer and
water main
installation is
complete.

       
  Red
(East
Central)
Area

Woodcrest Road
(600 block)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Water pipe
certification
documents were
submitted to WASD.
Paving with 1st layer
of asphalt is complete.
Sewer and water
main installation is
complete. 

    Glenridge Road
(662-699)
Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks.
Water pipe
certification
documents were
submitted to WASD.
Paving with 1st layer
of asphalt is complete.
Sewer and water
main installation is
complete.
    West Wood Drive
(Ridgewood to
east of Fernwood)

Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks.
Paving with 1st
layer of asphalt from
Glenridge to east
of Fernwood is
complete. Water
pipe certification
documents are
under review by
WASD. Paving
with 1st lift
of asphalt is
complete from
Ridgewood to
Glenridge.
Sewer and water
main installation is
complete.

    Woodcrest Road
(700 block)

Paving with 1st
layer of asphalt 
is complete.
Sewer and water
main installation
is complete.

    Glenridge Road
(700 block)
Paving with 1st
layer of asphalt
is complete.
Sewer and water
pipe installation is
complete.
    Fernwood Road
(600-700 blocks)

Paving with 1st
layer of asphalt
is complete
north and south of
Fernwood. Sewer
installation is
complete. Ductile
iron water main was
installed prior to
this project.

       
  Blue
(South)
Area
Ridgewood Road
(700 block)

Paving with 1st
layer of asphalt
is complete.
Sewer and water
main installation
is complete.

    Allendale Road
(780-799 area)

Sewer main
installation should
be complete by
Nov. 20 followed
by backfilling
excavated areas,
lateral installation
and roadway
restoration.
Water main
installation is
complete.

    West Mashta
Drive (Harbor
to east of
Fernwood)

Sewer main
installation is
complete. Road
closed from 30
West Mashta (near
Crandon) to
Fernwood for about
10 more days for
drainage and on-
street parking
improvements.
Otherwise road is
open to local
traffic only as
water services, new
fire hydrants
and sewer laterals
are installed, and
contractor and
WASD connect
West Mashta sewer
and water pipes,
respectively, to
side street pipes.
Road restoration
in area between
Ridgewood and
Fernwood will begin
this week; 1st lift
of asphalt expected
in 2-3 weeks.
Restoration will
begin between
Ridgewood and
Myrtlewood the
week of Nov. 30-
Dec. 4. New water
pipe certification
will follow beginning
with line flushing.
The cannon will be in
the Allendale area.
Water main
installation is
complete.
Equipment
and supplies will
be staged along
the swale during
work in this area.


Send this page to a friend

spacer
Lighthouse
Lighthouse
Friday, November 20, 2009
spacer
Search:
 
"To provide a safe, quality community environment for all islanders through responsible government"
separator separator

Village of Key Biscayne
88 W. McIntyre Street
Key Biscayne, FL 33149
305-365-5511

spacer
Sea Shell
Under Florida law, e-mail addresses are public records. If you do not want your email address released in response to a public records request,
do not send electronic mail to this entity. Instead, contact this office by phone or in writing.