| From November 17-24, 2009 |
| ZONE 1 |
|
STREET |
ACTIVITY
|
| |
NOTE: Meetings with the contractor regarding sewer certification continue. The revised set of sewer as-built drawings were approved by WASD. Approval of final conveyance document package pending; conveyance is expected by the end of 2009. Residents will be able to connect to sewer thereafter.
NOTE: Zone 1/Zone 4 and Reuse water weekly meetings
were discontinued as of November 25, 2008. Zone 1
construction is complete and water service has been
switched to the new pipes. The conveyance procedure will begin once as-builts are approved and the final inspection is complete. Residents cannot hook up to sewer until this process is complete. The Pump Station 131 hydrogen sulfide odor problem has been addressed with the installation of an ozone pump by WASD on June 26. See a June 20, 2009 letter to residents in the area of PS 131 from the Village Manager (PDF file) for details about the issue.
|
| |
Area 1
|
West Matheson
Drive |
WASD final review underway.
|
| |
|
Bay Lane |
WASD final review underway. |
| |
|
Harbor Point
Drive |
WASD final review underway.
|
| |
Area 2 |
Harbor Drive |
WASD final review underway.
|
| |
|
Sunset Circle
|
WASD final review underway. |
| |
|
Harbor Circle
|
WASD final review underway. |
| |
Area 3
|
West McIntyre
Street |
WASD final review underway. |
| |
|
Satinwood Drive
(South segment) |
WASD final review underway.
|
| |
|
West Enid Drive |
WASD final review underway. |
| |
|
Curtiswood Drive |
WASD final review underway.
|
| |
Area 4
|
Allendale Road
|
WASD final review underway.
|
| |
|
Sabal Palm Drive |
WASD final review underway. |
| |
|
Satinwood Drive
(North segment) |
WASD final review underway. |
| |
|
Beechwood Drive |
WASD final review underway.
|
| |
|
|
|
ZONE 4
|
|
STREET |
ACTIVITY |
| |
NOTE: County approval for resdeints to hook up to the sewer system was given on September 10, 2009. A sewer connection guide (PDF document) compiled by the Village is available online. A revised version of this document was posted on November 19, 2009.
Zone 1/Zone 4 and Reuse water weekly meetings were discontinued as of November 25, 2008. Zone 4 construction is complete and water service has been switched to the new pipes. Conveyance of the new sewer system from the Village to WASD occurred on August 24. |
| |
|
Caribbean Road |
Sewer hook-up allowed.
|
| |
|
Gulf Road |
Sewer hook-up allowed.
|
| |
|
Pacific Road |
Sewer hook-up allowed.
|
| |
|
Atlantic Road
|
Sewer hook-up allowed.
|
| |
|
East Heather
Drive |
Sewer hook-up allowed.
|
| |
|
Sonesta Drive
|
Sewer hook-up allowed. |
| |
|
|
|
ZONE 2/3
|
|
STREET |
ACTIVITY |
| |
NOTE: Paving with the 2nd (final) layer of asphalt will occur as soon as remedial concrete work is completed and West Mashta between Fernwood and Ridgewood is ready for the first layer of paving in about 2-3 weeks. Roads slated to get the 2nd paving pass include Harbor Drive north of West Wood, Harbor Lane, West Wood and the 600 blocks of Curtiswood, Allendale, Warren, Hampton, Woodcrest and Ridgewood.
NOTE: West Mashta Residents - Sewer work is underway and we need the locations of your
septic tanks so that the new
sewer system lateral to your property line is installed at the correct
location. This information has not been submitted for most of the homes along the
street. Those residents do not provide their septic tank locations
are hereby notified that the sewer lateral will be installed according to the project plan.
A tell-tale sign of the septic tank is the clean out pipe
protruding above the grass. Residents are advised to contact a plumber
or their clean-out service provider for assistance if necessary.
Please call Pietro Giacalone, the project Field Inspector for Zone 2/3, with your septic tank location information at (305) 216-5750 or email him at pietrog@c3ts.com.
NOTE: According to current progress, physical construction along West Mashta and the last piece of Allendale will be complete by the end of 2009. The earliest Zone 2/3 residents could hook up to the new sewer is in March 2010. This date is pending successful completion, certification and conveyance to WASD of the project. WASD has received paperwork from project officials to certify new sewer and water systems in 3 phases (geographic areas) to speed up the process. Phase 1 (between West Heather and West Enid from Warren to Fernwood, between West Wood and West Enid from Allendale to Woodcrest, and the new pump station, Key Biscayne K-8 Center and the Community Church) water certification is complete and service switched to new pipes; as-builts for water, sewer and the pump station have been submitted to WASD for review. In Phase 2 (from West Wood to West Mashta between Ridgewood and Harbor Drive, from Harbor Drive to just south of Harbor Circle, Harbor Lane, and Curtiswood and Allendale north of West Wood), the water certification process continues. Phase 3 includes the area from West Wood to West Mashta between
Ridgewood and Fernwood, Glenridge and Fernwood south of West Enid, and sewer extensions east of
Fernwood along West Enid, West Wood and West Mashta. Water pipe certification cannot be completed until West Mashta sewer is done and its new water main is connected to cross-street pipes.
NOTE: WASD is transferring water services to meters located in driveways and sidewalks along West Mashta and other streets. Expect local detours. The old meter will be removed once once the new meter is activated. Trans Florida will then revisit the areas to restore them to pre- project conditions.
NOTE: Please be patient with driveway restoration.
Tasks are performed by different subcontractors
specializing in brick pavers, poured or stamped
concrete, asphalt, etc. Not all repairs along a street
will be completed at the same time. For example,
all paver driveways/walkways will be repaired by a
paver specialist. Work on other types of surfaces will
be done on a different schedule by different
subcontractors.
NOTE: Residents in active work areas may experience low water pressure or sporadic outages during construction hours. Once service returns after a water interruption, let the water run until it is clear and air bubbles escape. You may prefer to use an outdoor spigot or faucet for this process. Sediment may clog the inside faucet filter so
periodic cleaning is advised.
|
| |
Yellow
(School)
Area |
West Enid Drive
(south of school)
|
Paving with 2nd layer, striping and signage installation is complete. Water service was switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
Ridgewood Road
(600 block)
|
Paving with 2nd
layer, striping and
signage installation
is complete. Water service was switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
West McIntyre
Street (100 block) |
Paving with 2nd
layer, striping and
signage installation
is complete. Water services were switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
Glenridge Road
(mid-500-600
blocks)
|
Paving with 2nd
layer, striping and
signage installation
is complete. Water services were switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
West Enid Drive
(east of school)
|
Paving with 2nd
layer, striping and
signage installation
is complete. Water services were switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
Fernwood Road
(570-598 block) |
Paving with 1st layer of asphalt is complete. Water services were switched from old to new pipes. Water and sewer main
installation is complete.
|
| |
|
West Enid Drive
(to new pump
station west of
school)
|
Paving with 2nd
layer, striping and
signage installation
is complete. The final Pump Station certification process is underway. Water services were switched from old to new pipes. Water and sewer main installation is complete.
|
| |
|
West Wood Drive
(Ridgewood Road
to Hampton Lane) |
Phase 2 water
certification is
complete. Paving with 1st layer of asphalt plus sewer and water main installation is complete.
|
| |
|
|
|
| |
Green
(West
Central)
Area
|
West Enid Drive
(200 block;
west of pump
station)
|
Placement of 2nd final layer of asphalt is complete. Water services were switched from old to new pipes. Water and sewer main
installation complete.
|
| |
|
Hampton Lane
(600 block) |
Paving with 2nd lift of asphalt will occur in about 2-3 weeks. Water services were switched from old to new pipes. Water and sewer main installation plus
paving with 1st layer of asphalt is
complete.
|
| |
|
Warren Lane
(600 block)
|
Paving with 2nd lift of asphalt will
occur in about 2-3 weeks. Water services were
switched from old
to new pipes. Water and sewer main installation plus paving with 1st layer of asphalt
is complete.
|
| |
|
Allendale Road
(600 block) |
Paving with 2nd lift of asphalt will
occur in about 2-3 weeks. Water services were
switched from old
to new pipes. Water and sewer main installation plus paving with 1st
layer of asphalt
is complete.
|
| |
|
Curtiswood Road
(650-698 area)
|
Paving with 2nd lift of asphalt will
occur in about 2-3 weeks. Concrete crews are repairing driveways, curbs and sidewalks. New water pipe certification is done for this area. Paving with 1st layer of asphalt and sewer and water main installation are complete.
|
| |
|
West Wood Drive
(Hampton Lane
to Myrtlewood
Lane) |
Paving with 2nd lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New water pipe
certification is
done for this area. Paving with 1st layer of asphalt is complete.
Sewer and water
main installation
is complete.
|
| |
|
Curtswood Road
(700 block) |
Paving with 1st layer of asphalt from from 755 area to Allendale is complete. New water pipe certification data
are under review. Paving with 1st layer of asphalt and sewer and water main installation is
complete.
|
| |
|
Allendale Road
(700 block)
|
Sewer installation
from West Mashta to 780 area should be completed by Nov. 20. Paving with 1st layer of asphalt to 780 area is complete. New water pipe
certification data
under review. Sewer main installation from from West Wood to 780 Allendale and is complete.
Water main installation is
complete.
|
| |
|
Myrtlewood Lane |
New water pipe
certification data
are under review. Paving with 1st layer of asphalt complete. Sewer and water main installation is complete.
|
| |
|
West Wood Drive
(Myrtlewood Lane
to Harbor Drive)
|
Paving with 2nd lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New water pipe
certification data
are under review. Paving with 1st layer of asphalt is complete. Sewer and water main installation is complete.
|
| |
|
Harbor Drive
(West Wood Drive
to West Mashta
Drive)
|
New water pipe
certification data
are under review. Road paved with 1st layer of asphalt. Sewer and water main installation is
complete.
|
| |
|
Harbor Drive
(West Wood Drive
to north of Harbor
Lane) |
Paving with 2nd lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New water pipe
certification is
done for this area. Road paved with 1st
layer of asphalt. Sewer and water main installation is complete.
|
| |
|
Harbor Lane
|
Paving with 2nd lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. New water pipe
certification is
done for this area. Road paved with 1st layer of asphalt. Sewer and water main installation is complete.
|
| |
|
|
|
| |
Orange
(North)
Area |
West Heather Drive (Fernwood to Warren)
|
West Heather was repaved as planned after completion of sewer work along side streets. |
| |
|
Hampton Lane
(400-500 block)
|
Paving with 2nd layer of asphalt and sewer and water main installation are complete. Water services were switched from old to new pipes.
|
| |
|
Ridgewood Road
(400-500 block) |
Paving with 2nd layer of asphalt is complete. Sewer main installation is complete. Water pipes were
installed previously
(during storm drainage project).
|
| |
|
Woodcrest Road
(400-500 block) |
Paving with 2nd layer of asphalt is complete. Water services were switched from old
to new pipes. Water and sewer main installation is complete.
|
| |
|
Glenridge Road
(400-500 block)
|
Paving with 2nd
layer of asphalt
is complete.
Sewer main installation is
complete. Water pipes were installed previously (during storm drainage
project). |
| |
|
Warren Lane
(400-500 block)
|
Paving with 2nd layer of asphalt is complete. Sewer main installation is
complete. Water pipes were installed previously (during storm drainage
project).
|
| |
|
Fernwood Road
(400-500 block)
|
Sewer manhole/ valves were raised prior to paving along Fernwood from the 422 area to Community Church. Paving with 1st lift of asphalt is complete in area of first phase
of sewer main installation.
Water services were switched to new pipes. Sewer and water main installation is
complete.
|
| |
|
West McIntyre
Street (200 block) |
Paving with 1st layer of asphalt is complete. Water services were switched to new pipes. Sewer and water main installation is
complete.
|
| |
|
|
|
| |
Red
(East
Central)
Area
|
Woodcrest Road
(600 block)
|
Paving with 2nd
lift of asphalt will
occur in about 2-3 weeks. Water pipe certification documents were submitted to WASD. Paving with 1st layer of asphalt is complete. Sewer and water main installation is complete.
|
| |
|
Glenridge Road
(662-699) |
Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. Water pipe certification
documents were submitted to WASD. Paving with 1st layer of asphalt is complete. Sewer and water main installation is complete. |
| |
|
West Wood Drive
(Ridgewood to
east of Fernwood)
|
Paving with 2nd
lift of asphalt will
occur in about 2-3
weeks. Concrete
crews repairing
driveways, curbs
and sidewalks. Paving with 1st layer of asphalt from Glenridge to east of Fernwood is complete. Water pipe certification
documents are under review by WASD. Paving with 1st lift of asphalt is complete from Ridgewood to Glenridge. Sewer and water main installation is complete.
|
| |
|
Woodcrest Road
(700 block) |
Paving with 1st
layer of asphalt
is complete. Sewer and water main installation is complete.
|
| |
|
Glenridge Road
(700 block) |
Paving with 1st
layer of asphalt
is complete. Sewer and water pipe installation is complete. |
| |
|
Fernwood Road
(600-700 blocks)
|
Paving with 1st
layer of asphalt
is complete north and south of Fernwood. Sewer installation is complete. Ductile iron water main was installed prior to this project.
|
| |
|
|
|
| |
Blue
(South)
Area
|
Ridgewood Road
(700 block) |
Paving with 1st layer of asphalt is complete.
Sewer and water
main installation
is complete.
|
| |
|
Allendale Road
(780-799 area)
|
Sewer main installation should be complete by Nov. 20 followed by backfilling excavated areas, lateral installation and roadway restoration. Water main installation is complete.
|
| |
|
West Mashta
Drive (Harbor
to east of Fernwood)
|
Sewer main installation is complete. Road closed from 30 West Mashta (near Crandon) to Fernwood for about 10 more days for drainage and on- street parking improvements. Otherwise road is open to local traffic only as water services, new fire hydrants and sewer laterals are installed, and contractor and WASD connect West Mashta sewer and water pipes, respectively, to side street pipes. Road restoration in area between Ridgewood and Fernwood will begin this week; 1st lift of asphalt expected in 2-3 weeks. Restoration will begin between Ridgewood and Myrtlewood the week of Nov. 30- Dec. 4. New water pipe certification will follow beginning with line flushing. The cannon will be in the Allendale area. Water main installation is
complete. Equipment and supplies will be staged along the swale during work in this area.
|